Humboldt increasing watermain repairs in 2023
The City of Humboldt is going to be doing more watermain replacements than planned for 2023.
Council approved over $700,000 in extra repairs for the year, mostly to deal with a section of pipe that had five breaks since Christmas.
“It’s about two blocks of pipe that was actually on Third Avenue,” Public Works Director Peter Bergquist said. “It’s kind of one year ahead of schedule, but we just we just don’t have confidence in the pipe.”
His report to council said the Third Avenue replacement project is estimated at $592,000.